Minimum opening size
At least 0.35 m² of unobstructed opening, with no dimension under 380 mm (Ontario Building Code 9.9.10.1).
Every egress quote follows an on-site measurement.
An excavated, retained space outside the new window sized to meet code clearance requirements.
A drain at the base of the well connected to the weeping tile so the well doesn't collect and hold water.
Installed for deeper wells so the window functions as a true emergency exit.
Sizes from the City of Ottawa egress window advisory (August 2025), based on the 2024 Ontario Building Code.
At least 0.35 m² of unobstructed opening, with no dimension under 380 mm (Ontario Building Code 9.9.10.1).
At least 550 mm of clear space in front of the window, with a clear way out of the well.
A well more than 1000 mm deep needs a ladder or steps to help you climb out.
The window has to stay open at the required size on its own, with no extra support.
A lintel sized to the opening and the load above it is required whenever the wall is cut.
We measure the wall and place the window clear of what's inside.
With the window size, well design and what your project needs for a permit.
We cut the opening, set the lintel, and frame and seal the window.
We dig and set the well, drain it to the weeping tile, and add a ladder where the depth needs one.
Straight answers to what Ottawa property owners ask before booking. Still unsure? Call us.
In most cases, yes. The window needs at least 0.35 m² of unobstructed opening with no dimension under 380 mm, and we confirm what your floor layout needs before quoting.
A typical single-window installation, including cutting the opening and building the well, usually takes one to a few days depending on site conditions.
Not when a properly sized structural lintel is installed to carry the load above the new opening, which is standard practice on every job.
It needs at least 550 mm of clear space in front of the window so you can get out, and a well more than 1000 mm deep needs a ladder or steps. We size the well to your opening.
Typically yes, since it affects the building's code-compliant egress – we can advise on what's needed for your specific project.
It is more difficult but often still possible, since the well excavation is what winter conditions affect most. Frozen or heavily snow-covered ground can delay scheduling, and we will tell you honestly if your specific site should wait for a thaw.